Cold weather concreting - how to avoid common mistakes

  •  

January saw the lowest temperatures in the UK since February 2016, and with the potential for more cold snaps on the way, it's a good time to review the procedures for placing concrete in cold weather.

If young concrete is allowed to cool to below freezing temperature, it is very likely that it will be damaged to the point of being entirely unfit for use. Should freshly-placed concrete be allowed to reach temperatures lower than 0°C, the water in the mix will freeze and expand; maintaining a temperature above zero degrees will help to ensure the intended strength of your concrete is reached- even if it is at a slower rate than was anticipated.

However, if the concrete is able to reach a strength of approximately 2N/mm2 it is likely to be able to resist the expansion and damage

It is important to note that even if temperatures don't reach freezing point, low temperatures will cause the concrete's strength to develop significantly slower than in warmer ambient temperatures.

This strength is typically reached within 48 hours for most mixes, should the concrete be kept above 5°C. So how, during cold weather, should you keep concrete sufficiently warm for the first 48 hours to ensure that this strength is able to develop?

Concrete should never be poured onto frozen ground, snow or ice. You can use heaters to thaw the ground prior to pouring concrete. If you plan to use heated enclosures, make certain they are both windproof and weatherproof.

Your concrete should include a maximum water to cement ratio, to limit bleeding. Additionally, you should not begin your final finishing operations whenever bleed water is still present.

It is important that formwork is not removed early, or else there is a risk that concrete in suspended slabs or beams could be too weak to carry its own weight due to the slower rate of strengthening the slow rate of strength development needs to be taken into account when calculating times for formwork removal.

Strength gain can be increased by minimising the amount of cement replacements or using admixtures- always seek the advice of your suppliers

If temperatures are low enough that frost is expected, useful protection measures include insulated or heated frost blankets and insulated formwork. Timber formwork often offers sufficient insulation by itself. Steel formwork is a poor insulator, and exposed surfaces should be covered with insulating material or temporary covers heated with space heaters.

For severe frost, it is best to heat the concrete (10°C) for delivery. If heated concrete is not available, it is better to delay your concreting until the ambient temperature rises to above 2°C.

When planning your concreting, you can obtain information on the likely temperatures from the Met Office, and should use this to plan your approach so you are never caught short or forced to delay your work. Armed with this information, you will be able to place your concrete perfectly, first time, whatever the weather.

By Andrew Bourne, Senior Area Sales Manager - Concrete at Sika

Visit: visit www.sika.co.uk

Additional Blogs

How micro-construction is delivering high-tech solutions for small-scale projects

The construction industry, historically defined by soaring high-rise buildings and vast infrastructure, is now undergoing a quiet revolution. A fast-expanding market segment, known as...

Read more

How traditional construction procurement undermines innovation

The construction industry has never liked change. While many things contribute to this, one of the most significant and often overlooked factors – and one that holds back innovation – is the...

Read more

Why carbon offsetting in construction Is a deceptive practice

The global construction industry continues to be under increasing pressure to address its substantial environmental footprint. As a major contributor to greenhouse gas emissions, responsible for a...

Read more

Submit your construction content here

Read more
Top
Login Logo